Difference between revisions of "Monterey Peninsula Water Project"
From CCoWS Wiki
(→Overview) |
(→Costs) |
||
Line 5: | Line 5: | ||
==Costs== | ==Costs== | ||
− | The MPWP has an estimated cost of $277 million<ref name="Project Overview"> http://www.watersupplyproject.org/overview</ref>. These costs will be allocated to | + | The MPWP has an estimated cost of $277 million<ref name="Project Overview"> http://www.watersupplyproject.org/overview</ref>. These costs will be allocated to following portions of the project: |
+ | |||
+ | |||
+ | {| border="1" class="wikitable" | ||
+ | |||
+ | ! scope="col"|Aspect of MPWP | ||
+ | ! scope="col"|Cost | ||
+ | |||
+ | |||
+ | |- | ||
+ | |||
+ | |Surface Intake Systems and Supply Return Facilities||$51M | ||
+ | |- | ||
+ | |Desalination Plant||$95M | ||
+ | |- | ||
+ | |Pipeline Facilities||$131M | ||
+ | |- | ||
+ | |Pre-Construction Cost||$8M | ||
+ | |- | ||
+ | |||
+ | |} | ||
==References== | ==References== | ||
<references/> | <references/> |
Revision as of 22:10, 1 April 2015
Overview
The Monterey Peninsula Water Project (MPWP) will consist of a series of slant wells[1] designed to pump water to a desalination facility in Marina. Current water (% use) in Monterey County stems from water which has been illegal obtained (citation). This project will prevent the legality problem of water...
Costs
The MPWP has an estimated cost of $277 million[1]. These costs will be allocated to following portions of the project:
Aspect of MPWP | Cost
|
---|---|
Surface Intake Systems and Supply Return Facilities | $51M |
Desalination Plant | $95M |
Pipeline Facilities | $131M |
Pre-Construction Cost | $8M |