With the installation of the Marina Peninsula Water Project, typical rate payers in the Monterey area can expect a 41% bill increase by 2018 <ref name="Rates"> http://www.amwater.com/caaw/Customer-Service/Rates-Information/monterey-water-supply-project.html</ref>.  The average citizen in the Monterey area uses approximately 74 units (10 cubic feet per unit).  These citizens monthly bill is expected to raise from $75 to an estimated $104 by 2018.  Citizens will be affected differently based on the levels of their water consumption.
  
 
==References==
 
==References==
 
<references/>
 
<references/>

Revision as of 22:30, 1 April 2015

Overview

The Monterey Peninsula Water Project (MPWP) will consist of a series of slant wellsdesigned to pump water to a desalination facility in Marina [1]. Current water (% use) in Monterey County stems from water which has been illegal obtained (citation). This project will prevent the legality problem of water...

Costs

The MPWP has an estimated cost of $277 million[1]. These costs will be allocated to following portions of the project:


Aspect of MPWP Cost


Surface Intake Systems and Supply Return Facilities $51M
Desalination Plant $95M
Pipeline Facilities $131M
Pre-Construction Cost $8M

Rate Changes

With the installation of the Marina Peninsula Water Project, typical rate payers in the Monterey area can expect a 41% bill increase by 2018 [2]. The average citizen in the Monterey area uses approximately 74 units (10 cubic feet per unit). These citizens monthly bill is expected to raise from $75 to an estimated $104 by 2018. Citizens will be affected differently based on the levels of their water consumption.

References

  1. 1.0 1.1 http://www.watersupplyproject.org/overview
  2. http://www.amwater.com/caaw/Customer-Service/Rates-Information/monterey-water-supply-project.html