==Overview==
 
==Overview==
  
The Monterey Peninsula Water Project (MPWP) will consist of a series of [[slant wells]] designed to pump water to a desalination facility in Marina <ref name="Project Overview"> http://www.watersupplyproject.org/overview</ref>.  Current water (% use) in Monterey County stems from water which has been illegal obtained (citation).  This project will prevent the legality problem of water...
+
The Monterey Peninsula Water Project (MPWP) was created to fill a growing need for water following the failure of the [[Regional Water Project]].  The MPWP will consist of a series of [[slant wells]] designed to pump water to a desalination facility in Marina <ref name="Project Overview"> http://www.watersupplyproject.org/overview</ref>.  Current water (% use) in Monterey County stems from water which has been illegal obtained (citation).  This project will prevent the legality problem of water...
  
 
==Costs==
 
==Costs==

Revision as of 22:35, 1 April 2015

Overview

The Monterey Peninsula Water Project (MPWP) was created to fill a growing need for water following the failure of the Regional Water Project. The MPWP will consist of a series of slant wells designed to pump water to a desalination facility in Marina [1]. Current water (% use) in Monterey County stems from water which has been illegal obtained (citation). This project will prevent the legality problem of water...

Costs

The MPWP has an estimated cost of $277 million[1]. These costs will be allocated to following portions of the project:


Aspect of MPWP Cost


Surface Intake Systems and Supply Return Facilities $51M
Desalination Plant $95M
Pipeline Facilities $131M
Pre-Construction Cost $8M

Rate Changes

With the installation of the Marina Peninsula Water Project, typical rate payers in the Monterey area can expect a 41% bill increase by 2018 [2]. The average citizen in the Monterey area uses approximately 74 units (10 cubic feet per unit). These citizens monthly bill is expected to raise from $75 to an estimated $104 by 2018. Citizens will be affected differently based on the levels of their water consumption.