Monterey Peninsula Water Supply Project (MPWSP)

From CCoWS Wiki
Revision as of 12:06, 2 April 2015 by Danm (Talk | contribs)

Jump to: navigation, search

Project Summary

Costs

The MPWP has an estimated cost of $277 million[1]. These costs will be allocated to following portions of the project:


Aspect of MPWP Cost


Surface Intake Systems and Supply Return Facilities $51M
Desalination Plant $95M
Pipeline Facilities $131M
Pre-Construction Cost $8M

Rate Changes

With the installation of the Marina Peninsula Water Project, typical rate payers in the Monterey area can expect a 41% bill increase by 2018 [2]. The average citizen in the Monterey area uses approximately 74 units (10 cubic feet per unit). These citizens monthly bill is expected to raise from $75 to an estimated $104 by 2018. Citizens will be affected differently based on the levels of their water consumption.

Current Status

Timeline

Links