Monterey Peninsula Water Supply Project (MPWSP)

From CCoWS Wiki
Revision as of 13:12, 2 April 2015 by Danm (Talk | contribs)

Jump to: navigation, search

Project Summary

Costs

The MPWP has an estimated cost of $277 million[1]. These costs will be allocated to following portions of the project:


Aspect of MPWP Estimated Cost


Surface Intake Systems and Supply Return Facilities $51M
Desalination Plant $95M
Pipeline Facilities $131M
Pre-Construction Cost $8M

Rate Changes

With the installation of the Marina Peninsula Water Project, typical rate payers in the Monterey area can expect a 41% bill increase by 2018 [2]. The average citizen in the Monterey area uses approximately 74 units (10 cubic feet per unit). These citizens monthly bill is expected to raise from $75 to an estimated $104 by 2018. Citizens will be affected differently based on the levels of their water consumption.

Current Status

Timeline

  • 2009
  • April 12, 2011
    • Investigation begins into the Regional Water Project, ultimately leading to that projects failure
  • April 23, 2012
    • CalAmfiled an application with the California Public Utilities Commission leading to the creation of the MPWP
  • October 10, 2012
    • Notice of Preparition of the project's EIR was released[4]
  • September 2014
  • January 30, 2015
    • Reached the final depth of the slant well testing its feasibility for the MPWP water source[6]
  • March 30, 2015
    • Completed test slant well successfully began pumping water and returning it to the ocean[7]
  • April 2015
    • Draft of the EIR is scheduled for release[4]
  • October 2015
    • Publication of the final EIR is scheduled for release[4]

Links

References

  1. http://www.watersupplyproject.org/overview
  2. http://www.amwater.com/caaw/Customer-Service/Rates-Information/monterey-water-supply-project.html
  3. http://www.dra.ca.gov/general.aspx?id=1875
  4. 4.0 4.1 4.2 http://www.cpuc.ca.gov/Environment/info/esa/mpwsp/index.html
  5. http://www.calwaterassn.com/california-american-water-awarded-1-million-grant-for-desalination-slant-test-well/
  6. http://www.montereyherald.com/opinion/20150227/ian-crooks-cal-am-test-slant-well-to-deliver-key-data
  7. http://www.ksbw.com/news/Cal-Am-desalination-well-now-pumping-water/32092494