* Initial Study- Once a public agency has determined that an activity qualifies as a project under CEQA and is not exempt, an initial study is prepared to determine whether the project may have a significant effect on the environment. The study also identifies possible measures to mitigate impacts to a less than significant level. Based on the outcome of the initial study, one of three documents will be prepared.
 
* Initial Study- Once a public agency has determined that an activity qualifies as a project under CEQA and is not exempt, an initial study is prepared to determine whether the project may have a significant effect on the environment. The study also identifies possible measures to mitigate impacts to a less than significant level. Based on the outcome of the initial study, one of three documents will be prepared.
 +
** Negative Declaration (ND)- This is completed when the initial study finds no substantial evidence that the project will have a significant effect on the environment.
 +
** Mitigated Negative Declaration (MND)- A MND can be prepared when the initial study has identified potentially significant environmental effects but revisions in the project plans or proposals would avoid potential effects or mitigate them to the level of non-significance. Revisions would have to be made and agreed upon before the initial study and negative declaration are released for public review, and there can be no substantial evidence that the revised project will have significant environmental effects.
 +
** Environmental Impact Report (EIR)- An EIR must be prepared when an initial study shows substantial evidence that significant effects may occur. The report provides information about those effects, possible actions to minimize those effects and outlines reasonable alternatives to the proposed project.
  
  

Revision as of 20:32, 1 April 2013

This page provides a general overview of California Environmental Quality Act (CEQA). This act requires any development with potential impact to the environment to go through a detailed review process.

History


Function of Law

Application Process

Flowchart outlining the general CEQA process CERES

Introduction to CEQAnet: online database of the State Clearinghouse which is part of the Governor's Office of Planning and Research.


  • Pre-Application Phase

Proposed project has been developed to the point where permit requirements need to be addressed. The potential applicant should identify the types of permits which will be required as well as the agencies associated with the project.

  • Application Phase

All required permitting applications are filled to the corresponding agencies. By this time a comprehensive project description must be completed. Agencies which receive applications are charged with concluding if applications are missing information or supporting documents.

  • Review Phase

Once an application is completed, a review procedure commences which evaluates the appropriate permitting guidelines and corresponding environmental investigation. Proposed projects are assessed to determine if CEQA applies to them.

Documents

The CEQA process entails the preparation of several documents. These can include:

  • Notice of Exemption (NOE)- This notice may be filed when a public agency determines that a project is exempt from CEQA and grants approval for said project. While not required, filing an NOE shortens the statute of limitations for challenging the agency decision from 180 days to 35 days. A NOE can be filed by either the lead agency or the applicant.
  • Initial Study- Once a public agency has determined that an activity qualifies as a project under CEQA and is not exempt, an initial study is prepared to determine whether the project may have a significant effect on the environment. The study also identifies possible measures to mitigate impacts to a less than significant level. Based on the outcome of the initial study, one of three documents will be prepared.
    • Negative Declaration (ND)- This is completed when the initial study finds no substantial evidence that the project will have a significant effect on the environment.
    • Mitigated Negative Declaration (MND)- A MND can be prepared when the initial study has identified potentially significant environmental effects but revisions in the project plans or proposals would avoid potential effects or mitigate them to the level of non-significance. Revisions would have to be made and agreed upon before the initial study and negative declaration are released for public review, and there can be no substantial evidence that the revised project will have significant environmental effects.
    • Environmental Impact Report (EIR)- An EIR must be prepared when an initial study shows substantial evidence that significant effects may occur. The report provides information about those effects, possible actions to minimize those effects and outlines reasonable alternatives to the proposed project.